Central East Transmission Development Overview

Overview

The proposed Central East Transmission Development project is within a large area stemming from Cold Lake south through the Battle River, Wainwright and Vegreville areas, and east to the Provost area (see Overview[AB1] ). Within this area, a variety of system upgrades have been proposed to meet growing demand for electricity from oil sands development and pipelines, and to interconnect proposed gas fired electricity generation as well as wind farms in the region. The upgrades include adding new transmission lines; adding new substations; adding new telecommunication towers; upgrading existing substations; and salvaging existing transmission lines and equipment.

Specific upgrades include:

  • Constructing approximately 195 kilometres of new transmission line
  • Salvaging approximately 95 kilometres of existing transmission line
  • Constructing two new substations
  • Modifying 12 existing substations
  • Constructing six new telecommunication towers

Detailed Project Information

The Central East Transmission Development project has been divided into a series of projects. More information regarding individual project segments is available for the following:

Active applications that have been submitted to the AUC can be viewed on the AUC website.

Central East Facility Projects - Planned

Status

Minor Alterations at the Irish Creek Substation Project update was sent to landholders and agencies on December 13, 2011
Bourque to Leming Lake Transmission Project Project update was sent to landholders and agencies on October 7, 2011


Project Update was sent to landholders and agencies on March 28, 2012.
Mahihkan to Bourque Transmission Project Project update was sent to landholders and agencies on October 7, 2011


Project Update was sent to landholders and agencies on March 28, 2012.

Bonnyville to Bourque Transmission Project

Project update was sent to landholders and agencies on October 19, 2011

 

Application filed with the AUC on April 27, 2012.

Bourque to Wolf Lake Transmission Project

Project update was sent to landholders and agencies on October 7, 2011

 

Project Update was sent to landholders and agencies on March 28, 2012.

Cold Lake Transmission Reinforcement Project

Project information was sent to landholders and agencies on October 7, 2011

Application filed with the AUC on March 7, 2012.

Project Update was sent to landholders and agencies on March 28, 2012.

Marguerite Lake to Wolf Lake Transmission Project

Application filed with AUC on February 3, 2012

Project Update was sent to landholders and agencies on March 28, 2012.

St. Paul Transmission Project

Project update was sent to landholders and agencies on February 27, 2012

Heisler Transmission Project

Application filed with the AUC on December 23, 2011

Kitscoty Transmission Project

Project update was sent to landholders and agencies on February 21, 2012

Lloydminster to Edgerton Transmission Project Project information was sent to landholders and agencies on October 26, 2011
Lloydminster Substation Telecommunications Project information was sent to landholders and agencies on November 1, 2011

Minor Alterations to the Whitby Lake Substation

Application filed with the AUC on December 23, 2011

ATCO Electric received AUC approval on April 19, 2012.

Alterations to the Vermilion Substation

Application filed with the AUC on October 13, 2011

Watt Lake Transmission Project

Application filed with the AUC on December 23, 2011

Decommissioning of line 6L06 Project information was sent to landholders and agencies on July 7, 2011

 

Note: Viewing the files linked here requires Adobe's Acrobat Reader or similar PDF viewer. Readers for most systems are available without charge from Adobe.

Maps and drawings tend to be larger files and will take a bit longer to download.  The readability of maps and drawings improves with closer views. Use the magnifying glass to zoom in on a specific section.  Should you experience a problem downloading the files or wish to be sent a copy please contact us by phone or
E-mail Us.

 

This page updated: April 30, 2012